Austin › contractor

Tumlinson Electric

26 permits on record in Austin (2025-09-08 → 2026-10-23)

Rank in Austin

Electrical#27 of 333 (30 days, 7 permits)#133 of 1218 (12 months, 23)

Permits per month, last 12 months

11
12
03
04
07
08
10

Recent permits

IssuedTradeAddressWorkStatus
2026-10-23Electrical6915 BRIDGE POINT PKWY BLDG 1 UNIT GARePlan: Expedited Review - New Construction of Parking Garage - Upper Clubhouse Level B1.Active ↗
2026-10-23Electrical6915 BRIDGE POINT PKWY BLDG 1 UNIT GARePlan: Expedited Review - New Construction of Parking Garage - Upper Clubhouse Level B2 - Private Garage for Residential Unit.Active ↗
2026-10-23Electrical6915 BRIDGE POINT PKWY BLDG 1ePlan: Expedited Review - New Construction of Upper Clubhouse with Garage.Active ↗
2026-10-23Electrical6915 BRIDGE POINT PKWY BLDG 1ePlan: Expedited Review - New Construction of Spa.Active ↗
2026-10-23Electrical6915 BRIDGE POINT PKWY BLDG 1ePlan: Expedited Review - New Construction of Pergola.Active ↗
2026-10-23Electrical6915 BRIDGE POINT PKWY BLDG 1ePlan: Expedited Review - New Construction of Vanishing Edge Pool.Active ↗
2026-10-23Electrical6915 BRIDGE POINT PKWY BLDG 1ePlan: Expedited Review - New Construction of Kids Pool.Active ↗
2026-08-25Electrical5730 1 2 MC NEIL DRIVETemporary Loop Refer to site plan SP-2016-0048DXActive ↗
2026-07-24Electrical3935 BRIGHT LIGHT BLVDePlan: Commercial Expedited Review - [APPROVED] Phase 1- Main Building to Include Riser Room (137 678 SF).Active ↗
2026-07-24Electrical3935 BRIGHT LIGHT BLVDePlan: Commercial Expedited Review - [APPROVED] Phase 1a- Main Building for Educational Site (215685 SF).Active ↗
2026-07-24Electrical3935 BRIGHT LIGHT BLVDePlan: Commercial Expedited Review - [APPROVED] Phase 1B- Scope of work to Include 3 Middle Sections for the Home side Bottom Row of the ProActive ↗
2026-07-23Electrical11525 STONEHOLLOW DR UNIT 200Partial interior remodeling of existing office building. Add new conference room and two new offices.Final ↗
2026-04-03Electrical2515 1 2 NORTHEAST DR UNIT TEMP1Temp power meters will be located on a rack Ref: 2025-053295 BP Temp1 - Portable Area A Temp2 - Portable Area B Temp3 - Portable Area CActive ↗
2026-03-26Electrical5405 PECAN BROOK DRNew walkway canopyFinal ↗
2026-03-16Electrical2208 1 2 BLUE MEADOW DRConstruction temp power for project site ref 2025-151791 BPFinal ↗
2025-12-05Electrical2206 BLUE MEADOW DRNonstructural renovations to an existing educational building-Building BActive ↗
2025-12-05Electrical2206 BLUE MEADOW DRNonstructural renovations to an existing educational building-Building CActive ↗
2025-12-05Electrical2206 BLUE MEADOW DRNonstructural renovations to an existing educational building-Building DActive ↗
2025-12-03Electrical2425 NORTHEAST DR BLDG REC34685 Sq. Ft. of Gym/Athletic Bldg. as part of the overall 149695 Sq. Ft. new YMLA school bond. The proposed design will accommodate a singlActive ↗
2025-12-03Electrical2515 NORTHEAST DR BLDG STOR1156 Sq. Ft. Athletic Storage as part of the overall 149695 sq. ft. new YMLA school bond program. The space will be used as a storage buildiActive ↗
2025-12-03Electrical2425 NORTHEAST DR2048 Sq. Ft. of Mechanical Building part of the overall 149695 Sq. Ft. new YMLA school bond program. The space will be used as the mechanicaActive ↗
2025-12-02Electrical2206 BLUE MEADOW DRConstruction of a new 67619 SF two story elementary school (Building A)Active ↗
2025-11-19Electrical1519 CORONADO HILLS DRePlan: Commercial Expedited Review - [Public Project] Interior Remodel to Existing CTE Campus including 2 New Secured Enty Vestibules RemodeFinal ↗
2025-09-30Electrical2206 BLUE MEADOW DRTEMPORARY BUILDING PERMIT scope of permit is limited to building and plumbing for early start of constructionFinal ↗
2025-09-15Electrical1211 E OLTORF STBuilding of a new three story educational main building at the southern end of the existing educational site (381246 SF) PuPR2 TNFM1 TNFM2 TActive ↗