Peoria › contractor
Car Charging Pros
3 permits on record in Peoria, 2026-02-09 to 2026-09-29
No open permits past 120 days on record
Pro keeps watching and emails you the moment one gets close.
Rank in Peoria
| Trade | 30 days | 90 days | 12 months |
|---|---|---|---|
| Electrical | #6 of 15 (1) | #9 of 43 (2) | #18 of 111 (2) |
Permits per month, last 12 months
Recent permits (3 of 3)
| Issued | Trade | Address | Work | Status |
|---|---|---|---|---|
| 2026-09-29 | Electrical | 7575 W SADDLEHORN RD | Installation of 1 48A Ev charger and 1 60A breaker in existing 200A meter main combo | Final ↗ |
| 2026-08-20 | Electrical | 12647 W FOREST PLEASANT PL | Installation of (1) EV charger 11.5 KW 48 A and (1) 60A 240V 2P breaker in existing 225A meter main combo | Final ↗ |
| 2026-02-09 | Other | 28373 N 128TH DR | 60A CIRCUIT FOR TESLA EVC | Final ↗ |